Springwater Substation

Wenatchee Foothills

Planning to Power - all the way to 2075

Substations are an integral part of Chelan PUD’s electrical power system, bringing together generation, transmission, and distribution. In alignment with the long-range vision of Imagine 2075, the Substation Program provides a strategic framework for proactively improving and expanding substation infrastructure. The PUD's Substation Program ensures we can continue delivering safe, reliable power to meet the evolving needs of Chelan County. 

Stay Engaged!

 Sign Up to be added to our email distribution list. 

Questions or Comments?
 Please email customeroutreach@chelanpud.org or
 call 509-661-8563.

Background

When an existing substation is consistently reaching 80% capacity, it triggers the PUD to begin looking into the need for a new substation. The PUD refers to this as an 80/20 Model and it initiates the process of identifying a location for a new substation and the associated transmission and distribution lines, in order to continue resilient and reliable service.

Chelan County PUD is planning for a new substation on the WSU Tree Fruit Research Center to serve the west Wenatchee area. The existing substations currently serving the area are nearing capacity. A new substation is needed to redistribute existing electrical load and serve future growth and development.

80-20 graphic

What's Happening Now?

  • Chelan PUD and WSU finalized real estate agreements necessary for substation construction.
  • Site studies and investigations will continue this year to further inform substation design and permitting. 
  • Permit applications will be submitted to the City of Wenatchee later this year. 
  • Substation construction is scheduled for 2028.

Anticipated Timeline


Substation Program Phase &
Anticipated Timeline

What's the PUD doing?

How are we engaging you?

1

 

PLAN

 

2020-2022

 


  • Identified the need for additional capacity
  • Identified potential alternative solutions

INFORM:
We kept the public informed.


2

 

ACQUIRE

 

2022-2025

 


  • Identified and scored potential sites
  • Acquired property and land rights
INVOLVE:
We gathered and considered feedback in decision making.


3

 

BUILD

 

2026-2030

 


  • Design of the substation and power lines 
  • Pursue appropriate permitting
  • Construct the substation and power lines
  • New infrastructure serving customers
INFORM:
We will keep the public informed during the construction process.





Past Year's Activities