Background
The equipment inside Chelan PUD's College Substation is reaching the end of its useful life and needs to be replaced. Over the next several years, we will begin planning to update the substation components and add new transmission switching equipment to improve system reliability for our customers.
The project will involve a phased rebuild of the substation, including replacing the two transformers and adding a new 115 kV ring bus inside the substation yard.
The anticipated timeline for this project is:
- 2027: Begin stakeholder outreach, design, permitting, and initiate procurement of long lead time items
- 2028: Phase 1 construction
- 2029: Phase 2 construction