Bavarian Substation

Bavarian webpage photo

Planning to Power - all the way to 2075

Substations are an integral part of Chelan PUD’s electrical power system, bringing together generation, transmission, and distribution. In alignment with the long-range vision of Imagine 2075, the Substation Program provides a strategic framework for proactively improving and expanding substation infrastructure. The PUD's Substation Program ensures we can continue delivering safe, reliable power to meet the evolving needs of Chelan County. 

Stay Engaged!

 Sign Up to be added to our email distribution list. 

Questions or Comments?
 Please email customeroutreach@chelanpud.org or
 call 509-661-8563.


Background

When an existing substation is consistently reaching 80% capacity, it triggers the PUD to begin looking into the need for a new substation. The PUD refers to this as an 80/20 Model and it initiates the process of identifying a location for a new substation and the associated transmission and distribution lines, in order to continue resilient and reliable service.

Chelan County PUD has been working with the community since 2015 to construct a new substation and associated transmission lines to serve the Leavenworth area. The existing double-bank substation serving the area is nearing capacity. In May 2017, the PUD, along with community input, selected a site at the intersection of North Road and Chumstick Highway for the new substation.

80-20 graphic


What's Happening Now?

  • Upon completion of environmental reviews, Chelan PUD applied for and received a Conditonal Use Permit.
  • Site preparation work is expected to begin in September 2025.
  • Easement acquisition for transmission and distribution routes are nearly complete.
  • Chelan PUD will inform stakeholders of upcoming construction activities.

Anticipated Timeline


Substation Program Phase &
Anticipated Timeline

What's the PUD doing?

How are we engaging you?

1

 

PLAN

 

2020-2024

 


  • Identified the need for additional capacity
  • Identified potential alternative solutions

INFORM:
We will keep the public informed.


2

 

ACQUIRE

 

2020-2024

 


  • Identify and score potential sites
  • Acquire property and land rights
INVOLVE:
We will gather and consider feedback in decision making.


3

 

BUILD

 

2020-2024

 


  • Design of the substation and power lines 
  • Pursue appropriate permitting
  • Construct the substation and power lines
  • New infrastructure serving customers
CONSULT:
We will listen to and acknowledge concerns during the design process.


INFORM:
We will keep the public informed during the construction process.