WHAT:
Chelan County PUD is upgrading the electrical infrastructure at Washington West Condos. These improvements will replace aging equipment to provide more reliable power and long-term service. Please refer to the highlighted area on the map to see the locations impacted by this work.
WHEN & WHAT TO EXPECT:
Project Start & Duration: Week of June 23rd through mid-July.
Working Hours: Monday through Thursday, from 8 a.m. to 4 p.m.
Scheduled Power Outages: Some planned outages may be necessary. Affected customers will be notified in advance.
Construction Activities: Our contractor, Trenchless, will use directional boring and digging methods. Chelan PUD crews will install new underground cables and electrical equipment. You will notice trucks, crews, and construction noise during work hours.
Minimal Visual Impact: Upgraded equipment will be installed in the same locations as the current system. Landscape will be restored at project completion.