FERC Process

Rock Island Process – Integrated Licensing Process (ILP)

Regulatory Milestones                                                                                              Timeline
Chelan PUD files PAD and NOI                                                                                   July 2023 - Dec. 2023
Draft License Application or Preliminary Licensing Proposal due to FERC         August 2026     
Filing of Application due to FERC                                                                               December 2026
Current Rock Island License Expires                                                                         December 2028

FERC Guidance Materials