Rock Island Process – Integrated Licensing Process (ILP)
Regulatory Milestones Timeline
Chelan PUD files PAD and NOI July 2023 - Dec. 2023
Draft License Application or Preliminary Licensing Proposal due to FERC August 2026
Filing of Application due to FERC December 2026
Current Rock Island License Expires December 2028
FERC Guidance Materials