Mill and West Benton street work

Work begins soon on Mill and West Benton streets

Chelan County PUD will be replacing poles and wires along Mill and West Benton streets in Leavenworth starting in mid-February. This project will increase reliability and upgrade equipment.

What to expect

  • PUD crews will conduct this work, with the exception of any tree work required. Tree work will be completed by contractors.
  • Power outages may be needed along West Benton Street and affected customers will be notified with details prior to any outage.
  • Customers, not on West Benton Street, are receiving this postcard as awareness for traffic impacts and will only be impacted by a very short outage related to this project.
  • New power poles will be placed adjacent to existing poles.
  • Flaggers will be present to direct traffic. We do not anticipate any long delays. For safety, please follow flagger instructions and roadway signs.
  • Once work begins, it will last about 4-5 weeks.
  • Work will occur Monday – Friday, from 8 a.m. to 4 p.m.
Questions?

If you have questions or comments about the project, please email customeroutreach@chelanpud.org or call (509) 661-8563.