SCHEDULE UPDATE

The PUD postponed construction of the project due to wet weather conditions. Allowing the area to dry out provided the crew a safer and more efficient working environment.

  • PUD crews will begin work on Tuesday, August 15
  • Work is expected to last about two weeks
  • Working hours are generally Tuesday-Thursday, 7:30 a.m.-3:30 p.m.
  • You will hear typical construction noise during working hours
  • Crews and equipment will take up much of the narrow roadway during working hours
  • We anticipate periodic road closures between 8 a.m. and 2 p.m.
  • Residents are encouraged to plan travel around these hours Tuesday and Thursday
  • If you need assistance with thru travel during a road closure, please contact Superintendent, Cody Murdock at (509) 860-4797


WHAT:
Chelan County PUD crews will begin replacing poles and stringing new wire along a half-mile stretch of Ranger Rd. near Leavenworth from the Ski Hill Dr. intersection to the end of the road.

WHY:  This project will improve reliability, replace aging equipment, and improve potentially low clearances on some lines.

QUESTIONS:

Send questions to contactus@chelanpud.org
or call the project engineer Chris Moser at (509)-661-4128