Rocky Reach Meeting Schedules

Public/Agency (Full Relicensing Team) Meetings

Working Group Meetings
Natural Sciences
(Fisheries, Water Quality, Wildlife, Botanical)   Cultural/Historical
Erosion   Social Sciences
(Socioeconomics, Recreation, Aesthetics, Land Management)
Settlement Group     Technical Group

2001 At A Glance
Jan    Feb    Mar   April    May     June    July    Aug   Sept     Oct    Nov     Dec

1999     2000     2001      2002      2003      2004     2005

January 18, 2001
Working Group Meeting: Social Sciences: Recreation / Economics - (Chelan PUD, Wenatchee) Purpose is to discuss draft study plans and reports
January 23, 2001 Working Group Meeting: Cultural Resources - (Wenatchee, Washington) Purpose is to review schedule and comment on final study plan
January 25, 2001
Public / Agency Meeting - (Chelan PUD Auditorium, Wenatchee) Purpose is to provide update on studies currently under way and for 2001 and on working group meetings
February 16, 2001 Working Group Meeting: Cultural Resources - (Chelan, Washington) Purpose is to finalize study methods for 2001 fieldwork
February 21, 2001 Working Group Meeting: Natural Sciences: Fisheries / Wildlife / Water Quality Resources - (Rocky Reach 4th Floor Conference Room, Wenatchee) Purpose is to review 2000 study reports and 2001study plan outlines for 2001, tour bull trout trap facilities
February 22, 2001
Public / Agency Meeting - Canceled: Next meeting on March 29, 2001
February 22, 2001
HCP Workshop - (Chelan PUD Auditorium, Wenatchee) Purpose is to present an overview of the of the process and documentation associated with the Habitat Conservation Plan
March 20, 2001
Working Group Meeting: Social Sciences: Recreation / Economics - (Chelan PUD, Wenatchee) Purpose is to review the draft Recreation Inventory Analysis and discuss the FPA, mandatory conditioning and cumulative impacts
March 29, 2001
Public / Agency Meeting - (Chelan PUD Auditorium, Wenatchee) Purpose is to provide update on studies currently under way and for 2001 and on working group meetings
April 19, 2001
Public / Agency Meeting - Canceled: Next meeting on May 24, 2001
May 15, 2001 Working Group Meeting: Social Sciences: Recreation / Economics - (Chelan PUD, Wenatchee) Purpose is to review the Recreation Inventory Summary and Needs Forecast Analysis draft reports and the guidelines for assessing cumulative impacts
May 21, 2001 Working Group Meeting: Erosion - (Chelan PUD, Wenatchee) Purpose is to review comments on the Shoreline Erosion Inventory draft report and discuss possible tasks
May 24, 2001 Public / Agency Meeting - (Chelan PUD Auditorium, Wenatchee) Purpose is to provide update on studies currently under way and on working group meetings
June 8, 2001 Working Group Meeting: Natural Sciences: Fisheries / Wildlife / Water Quality Resources - (Chelan PUD, Wenatchee) Purpose is to provide update on ongoing studies and to develop a list of cumulative effects
June 26, 2001 Working Group Meeting: Cultural Resources - (Wenatchee, Washington) Purpose is to provide update of ongoing studies, outline upcoming tasks and develop CRMP
June 28, 2001 Public / Agency Meeting - Canceled: Next meeting on Sept. 27, 2001
July 26, 2001 Public / Agency Meeting - Canceled: Next meeting on Sept. 27, 2001
July 27, 2001 Working Group Meeting: Social Sciences - Canceled
August 15, 2001 Working Group Meeting: Social Sciences: Recreation / Economics - (Chelan PUD, Wenatchee) Purpose is to review the second draft study reports and continue discussion of cumulative impacts
August 23, 2001 Public / Agency Meeting - Canceled: Next meeting on Sept. 27, 2001
September 27, 2001 Public / Agency Meeting - (Chelan PUD Auditorium, Wenatchee) Purpose is to provide update on ongoing studies and working group meetings and to discuss upcoming studies for 2002
September 27, 2001 Working Group Meeting: Social Sciences: Recreation / Economics - (Chelan PUD, Wenatchee) Purpose is to review and discuss final study reports and review comments received.
October 12, 2001 Working Group Meeting: Cultural Resources - (Wenatchee, Washington) Purpose is to review study results and develop CRMP
October 23, 2001 Working Group Meeting: Natural Sciences: Fisheries / Wildlife / Water Quality Resources - (Chelan PUD, Wenatchee) Purpose is to provide update on ongoing studies, develop a cumulative effects list and identify 2002 studies
Oct/Nov/Dec 2001 Public / Agency Meeting - Canceled: Next meeting in January 2002
November 9, 2001 Working Group Meeting: Cultural Resources - (Wenatchee, Washington) Purpose is to review study results
November 30, 2001 Working Group Meeting: Erosion - (Chelan PUD, Wenatchee) Purpose is to discuss remaining tasks regarding erosion control plan and notebook
December 14, 2001 Working Group Meeting: Canceled 

 

Long-term Schedule
2000-2002 Conduct Studies
2003 Draft License and Environmental Assessment
2004 PUD Submits Final License and Environmental Assessment
2004-2006 FERC Review and Processing of License Application Environmental Assessment
2006 Existing License Expires/New License Issued