Lake Chelan Meeting Schedules

Public/Agency (Full Relicensing Team) Meetings

Working Group Meetings
Natural Sciences_(Wildlife/Botanical, Fisheries, Water Quality)    Cultural/Historical
Erosion   
Social Sciences (Socioeconomics, Recreation, Aesthetics, Land Management)

2001 At A Glance
Jan    Feb    Mar   April    May     June    July    Aug   Sept     Oct    Nov     Dec

1998      1999     2000     2001      2002

January 23, 2001 Working Group Meeting: Cultural Resources - (Wenatchee, Washington) Purpose is to develop field study methods for 2001 fieldwork.
January 24, 2001 Working Group Meeting: Natural Sciences: Fisheries / Wildlife / Water Quality Resources - (Chelan, Washington) Purpose is to discuss various flow proposals and review study plans for 2001
January 24, 2001 Public / Agency Meeting - (Chelan, Washington) Purpose is to update status of draft PDEA and License Application and to decide process issues
January 31, 2001 Working Group Meeting: Social Sciences: Recreation / Aesthetics - (Chelan, Washington) Purpose is to review conceptual outline and recommendations completed by the drafting committee for implementation of the endowment fund
January 31, 2001 Working Group Meeting: Erosion - (Chelan PUD, Wenatchee) Purpose is to discuss the draft erosion control methods notebook and cost estimates and review study reports and plans
February 16, 2001 Working Group Meeting: Cultural Resources - (Chelan, Washington) Purpose is to receive final comments on 2001 study plan
February 28, 2001 Working Group Meeting: Natural Sciences: Fisheries / Wildlife / Water Quality Resources - (Chelan, Washington) Purpose is to receive flow issues updates, discuss fishery/LWD management plans and select temperature model
February 28, 2001 Public / Agency Meeting - (Chelan, Washington) Purpose is to discuss process issues regarding the PDEA and first-draft License Terms and Conditions
March 13, 2001 Working Group Conference Call: Erosion - (Chelan PUD, Wenatchee) Purpose is to discuss the erosion control plans and cost estimates
March 21, 2001 Working Group Meeting: Natural Sciences: Fisheries / Wildlife / Water Quality Resources - (Chelan, Washington) Purpose is to receive update on flow issues, select appropriate temperature model for bypassed reach, discuss LWD management plan and Lake Chelan fishery management plan issues
March 22, 2001 Working Group Meeting: Social Sciences: Recreation / Aesthetics - (Chelan, Washington) Purpose is to review identified PMEs, the endowment fund concept and next steps
March 28, 2001 Public / Agency Meeting - (Chelan, Washington) Purpose is to discuss process issues regarding the first-draft License Terms and Conditions and present updates on working groups
April 10, 2001 Working Group Meeting: Natural Sciences: Fisheries / Wildlife / Water Quality Resources - (Chelan, Washington) Purpose is to discuss development of the monitoring and evaluation program for the Lake Chelan CFMP
April 18, 2001 Public / Agency Meeting - Canceled: Next meeting on May 23, 2001
April 19, 2001 Working Group Meeting: Erosion - (Chelan PUD Office, Chelan) Purpose is to discuss the erosion control plans, Stehekin sedimentation issues and draft license articles
May 2, 2001 Working Group Meeting: Natural Sciences: Fisheries / Wildlife / Water Quality Resources - (Chelan, Washington) Purpose is to receive update on caucus flow issues, discuss LWD management plan and Lake Chelan fishery management plan issues
May 17, 2001 Working Group Meeting: Social Sciences: Recreation / Aesthetics - (Chelan, Washington) Purpose is to review comments on draft license articles and present update from the endowment fund drafting committee
May 23, 2001
(9 am to noon)
Formal Public Meeting Notice - (Chelan PUD, Wenatchee)  PDEA and License Application  - Opportunity for local organizations and general public to review and comment
May 23, 2001
(6:30 pm to 9 pm)
Formal Public Meeting Notice - (Chelan, Washington)  PDEA and License Application - Opportunity for local organizations and general public to review and comment
May 31, 2001 Working Group Meeting: Social Sciences: Recreation / Aesthetics - (Chelan, Washington) Purpose is to continue discussions related to the PDEA, draft license terms and conditions and endowment fund
June 7, 2001 Working Group Meeting: Natural Sciences: Fisheries / Wildlife / Water Quality Resources - Canceled
June 19, 2001 Working Group Meeting: Social Sciences: Recreation / Aesthetics - (Chelan, Washington) Purpose is to continue discussions related to the PDEA, draft license terms and conditions and endowment fund
June 22, 2001 Working Group Meeting: Erosion - (Chelan PUD , Wenatchee) Purpose is to discuss the erosion control plans, Stehekin channel monitoring plan and draft license articles
June 26, 2001 Working Group Meeting: Cultural Resources - (Wenatchee, Washington) Purpose is to provide update of ongoing studies, outline upcoming tasks and develop CRMP
June 27, 2001 Public / Agency Meeting - (Chelan, Washington) Purpose is to present updates on working groups
July 9, 2001 Working Group Meeting: Natural Sciences: Fisheries / Wildlife / Water Quality Resources - (Chelan, Washington) Purpose is to receive update on flow issues from the caucus and receive update on the CFMP
July 13, 2001 Working Group Meeting: Social Sciences: Recreation / Aesthetics - (Chelan, Washington) Purpose is to continue discussions related to draft license terms and conditions and endowment fund
July 25, 2001 Public / Agency Meeting - (Chelan, Washington) Purpose is to update all parties on working group progress
August 6, 2001 Working Group Meeting: Natural Sciences: Fisheries / Wildlife / Water Quality Resources - (Chelan, Washington) Purpose is to discuss flow and enhancement proposals and associated costs
August 9, 2001 Working Group Meeting: Social Sciences: Recreation / Aesthetics - (Chelan, Washington) Purpose is to continue discussions related to draft license terms and conditions, the endowment fund and the recreation management plan
August 22, 2001  Public / Agency Meeting: (Chelan, Washington) Purpose is to understand major revisions to PDEA and proposed license terms and conditions and update all parties on working group progress
August 23, 2001 Working Group Meeting: Erosion - (Chelan PUD , Wenatchee) Purpose is to discuss the LWD management and erosion control plans
September 12, 2001 Working Group Meeting: Natural Sciences: Fisheries / Wildlife / Water Quality Resources - (Chelan, Washington) Purpose is to discuss management plans and entrainment
September 13, 2001 Working Group Meeting: Social Sciences: Recreation / Aesthetics - (Chelan, Washington) Purpose is to continue discussions related to the draft license articles, PDEA, the endowment fund and the recreation management plan
September 21, 2001 Working Group Meeting: Erosion - (Chelan PUD , Wenatchee) - Canceled 
September 24, 2001 Working Group Meeting: Erosion - (Chelan PUD , Wenatchee) Purpose is to discuss the LWD, erosion control and other management plans
September 26, 2001  Public / Agency Meeting - (Chelan, Washington) Purpose is to review next steps in process for preparing agreement and update all parties on working group progress
October 4, 2001 Working Group Meeting: Natural Sciences: Fisheries / Wildlife / Water Quality Resources - (Wenatchee, Washington) Purpose is to continue discussions on management plans and entrainment
October 12, 2001 Working Group Meeting: Cultural Resources - (Wenatchee, Washington) Purpose is to review study results and develop CRMP
October 24, 2001  Public / Agency Meeting - (Chelan, Washington) Purpose is to continue next steps for preparing agreement and update all parties on working group progress on the management plans
October 30, 2001 Working Group Meeting: Social Sciences: Recreation / Aesthetics - (Chelan, Washington) Purpose is to discuss the recreation management plan, PDEA,  license terms and the local Endowment Fund.
November 8, 2001 Working Group Meeting: Natural Sciences: Fisheries / Wildlife / Water Quality Resources - (Chelan, Washington) Purpose is to discuss management plans, temperature modeling and any remaining issues
November 9, 2001 Working Group Meeting: Cultural Resources - (Wenatchee, Washington) Purpose is to review study comments and develop CRMP
November 27, 2001 Working Group Meeting: Social Sciences: Recreation / Aesthetics - (Chelan, Washington) Purpose is to review draft finals of recreation plan and PDEA social resources sections
November  28, 2001 Public / Agency Meeting - Canceled 
December 5, 2001 Working Group Meeting: Natural Sciences: Fisheries / Wildlife / Water Quality Resources - (Chelan, Washington) Purpose is to discuss changes to final management plans and to review PDEA sections and schedule
December 14, 2001 Working Group Meeting: Cultural Resources - Canceled 
December 19, 2001  Public / Agency Meeting - (Chelan, Washington) Purpose is to discuss final draft comprehensive management plans, review progress on agreement documents and discuss revisions to PDEA
*Tentative
Long-term Schedule
Summer 2000 Conduct studies
January 2001 Review copy, Draft License and Environmental Assessment
April 2001 Draft License and Environmental Assessment
December 2001 Review copy, Final License and Environmental Assessment
March 2002 Submit Final License Application and Environmental Assessment