2001 At A Glance
Jan Feb
Mar April
May June
July Aug Sept
Oct Nov
Dec
1998
1999 2000
2001 2002
| January
23, 2001 |
Working Group Meeting: Cultural Resources -
(Wenatchee, Washington) Purpose is to develop field study methods for 2001
fieldwork.
|
| January
24, 2001 |
Working Group Meeting:
Natural Sciences: Fisheries / Wildlife / Water Quality
Resources -
(Chelan, Washington) Purpose is to discuss various flow proposals and
review study plans for 2001 |
| January
24, 2001 |
Public
/ Agency Meeting - (Chelan, Washington) Purpose is to update status of
draft PDEA and License Application and to decide process issues |
| January
31, 2001 |
Working Group Meeting: Social Sciences: Recreation / Aesthetics -
(Chelan, Washington) Purpose is to review conceptual outline and
recommendations completed by the drafting committee for implementation
of the endowment fund |
| January
31, 2001 |
Working Group Meeting:
Erosion - (Chelan PUD, Wenatchee) Purpose is to
discuss the draft erosion control methods notebook and cost estimates
and review study reports and plans |
| February
16, 2001 |
Working Group Meeting: Cultural Resources -
(Chelan, Washington) Purpose is to receive final comments on 2001
study plan |
| February
28, 2001 |
Working Group Meeting:
Natural Sciences: Fisheries / Wildlife / Water Quality
Resources -
(Chelan, Washington) Purpose is to receive flow issues updates,
discuss fishery/LWD management plans and select temperature model |
| February
28, 2001 |
Public
/ Agency Meeting - (Chelan, Washington) Purpose is to discuss
process issues regarding the PDEA and first-draft License Terms and
Conditions |
| March
13, 2001 |
Working Group
Conference Call:
Erosion - (Chelan PUD, Wenatchee) Purpose is to
discuss the erosion control plans and cost estimates |
| March
21, 2001 |
Working Group Meeting:
Natural Sciences: Fisheries / Wildlife / Water Quality
Resources -
(Chelan, Washington) Purpose is to receive update on flow issues,
select appropriate temperature model for bypassed reach, discuss LWD
management plan and Lake Chelan fishery management plan issues |
| March
22, 2001 |
Working Group Meeting: Social Sciences: Recreation / Aesthetics -
(Chelan, Washington) Purpose is to review identified PMEs, the
endowment fund concept and next steps |
| March
28, 2001 |
Public
/ Agency Meeting - (Chelan, Washington) Purpose is to discuss
process issues regarding the first-draft License Terms and
Conditions and present updates on working groups |
| April
10, 2001 |
Working Group Meeting:
Natural Sciences: Fisheries / Wildlife / Water Quality
Resources -
(Chelan, Washington) Purpose is to discuss development of the
monitoring and evaluation program for the Lake Chelan CFMP |
| April
18, 2001 |
Public
/ Agency Meeting - Canceled: Next meeting on May 23, 2001 |
| April
19, 2001 |
Working Group
Meeting:
Erosion - (Chelan PUD Office, Chelan) Purpose is to
discuss the erosion control plans, Stehekin sedimentation issues and draft license articles |
| May
2, 2001 |
Working Group Meeting:
Natural Sciences: Fisheries / Wildlife / Water Quality
Resources -
(Chelan, Washington) Purpose is to receive update on caucus flow issues,
discuss LWD
management plan and Lake Chelan fishery management plan issues |
| May
17, 2001 |
Working Group Meeting: Social Sciences: Recreation / Aesthetics -
(Chelan, Washington) Purpose is to review comments on draft license
articles and present update from the endowment fund drafting committee |
May
23, 2001
(9 am to noon) |
Formal
Public Meeting Notice - (Chelan PUD, Wenatchee) PDEA and
License Application - Opportunity for local organizations and general public to review and comment |
May
23, 2001
(6:30 pm to 9 pm) |
Formal
Public Meeting Notice - (Chelan, Washington) PDEA and License
Application
- Opportunity for local organizations and general public to review and comment |
| May
31, 2001 |
Working Group Meeting: Social Sciences: Recreation / Aesthetics -
(Chelan, Washington) Purpose is to continue discussions related to the
PDEA, draft license terms and conditions and endowment fund |
| June
7, 2001 |
Working Group Meeting:
Natural Sciences: Fisheries / Wildlife / Water Quality
Resources - Canceled |
| June
19, 2001 |
Working Group Meeting: Social Sciences: Recreation / Aesthetics -
(Chelan, Washington) Purpose is to continue discussions related to the
PDEA, draft license terms and conditions and endowment fund |
| June
22, 2001 |
Working Group
Meeting:
Erosion - (Chelan PUD , Wenatchee) Purpose is to
discuss the erosion control plans, Stehekin channel monitoring plan and draft license articles |
| June
26, 2001 |
Working Group Meeting: Cultural Resources -
(Wenatchee, Washington) Purpose is to provide update of ongoing
studies, outline upcoming tasks and develop CRMP |
| June
27, 2001 |
Public
/ Agency Meeting - (Chelan, Washington) Purpose is to present updates on working groups |
| July
9, 2001 |
Working Group Meeting:
Natural Sciences: Fisheries / Wildlife / Water Quality
Resources - (Chelan, Washington) Purpose is to receive update on
flow issues from the caucus and receive update on the CFMP |
| July
13, 2001 |
Working Group Meeting: Social Sciences: Recreation / Aesthetics -
(Chelan, Washington) Purpose is to continue discussions related to draft license terms and conditions and endowment fund |
| July
25, 2001 |
Public
/ Agency Meeting - (Chelan, Washington) Purpose is to update all
parties on working group progress |
| August
6, 2001 |
Working Group Meeting:
Natural Sciences: Fisheries / Wildlife / Water Quality
Resources - (Chelan, Washington) Purpose is to discuss flow and
enhancement proposals and associated costs |
| August
9, 2001 |
Working Group Meeting: Social Sciences: Recreation / Aesthetics -
(Chelan, Washington) Purpose is to continue discussions related to draft license terms and conditions,
the endowment fund and the recreation management plan |
| August
22, 2001 |
Public
/ Agency Meeting: (Chelan, Washington) Purpose is to understand
major revisions to PDEA and proposed license terms and conditions and
update all parties on working group progress |
| August
23, 2001 |
Working Group
Meeting:
Erosion - (Chelan PUD , Wenatchee) Purpose is to
discuss the LWD management and erosion control plans |
| September
12, 2001 |
Working Group Meeting:
Natural Sciences: Fisheries / Wildlife / Water Quality
Resources - (Chelan, Washington) Purpose is to discuss management
plans and entrainment |
| September
13, 2001 |
Working Group Meeting: Social Sciences: Recreation / Aesthetics -
(Chelan, Washington) Purpose is to continue discussions related to the
draft license articles, PDEA, the endowment fund and the recreation management plan |
| September
21, 2001 |
Working Group
Meeting:
Erosion - (Chelan PUD , Wenatchee) - Canceled |
| September
24, 2001 |
Working Group
Meeting:
Erosion - (Chelan PUD , Wenatchee) Purpose is to
discuss the LWD, erosion control and other management plans |
| September
26, 2001 |
Public
/ Agency Meeting - (Chelan, Washington) Purpose is to review
next steps in process for preparing agreement and update all parties
on working group progress |
| October
4, 2001 |
Working Group Meeting:
Natural Sciences: Fisheries / Wildlife / Water Quality
Resources - (Wenatchee, Washington) Purpose is to continue discussions
on management
plans and entrainment |
| October
12, 2001 |
Working Group Meeting: Cultural Resources -
(Wenatchee, Washington) Purpose is to review study results and develop CRMP |
| October
24, 2001 |
Public
/ Agency Meeting - (Chelan, Washington) Purpose is to continue next steps
for preparing agreement and update all parties
on working group progress on the management plans |
| October
30, 2001 |
Working Group Meeting: Social Sciences: Recreation / Aesthetics -
(Chelan, Washington) Purpose is to discuss the recreation management
plan, PDEA, license terms and the local Endowment Fund. |
| November
8, 2001 |
Working Group Meeting:
Natural Sciences: Fisheries / Wildlife / Water Quality
Resources - (Chelan, Washington) Purpose is to discuss management
plans, temperature modeling and any remaining issues |
| November
9, 2001 |
Working Group Meeting: Cultural Resources -
(Wenatchee, Washington) Purpose is to review study comments and develop CRMP |
| November
27, 2001 |
Working Group Meeting: Social Sciences: Recreation / Aesthetics -
(Chelan, Washington) Purpose is to review draft finals of recreation
plan and PDEA social resources sections |
| November
28, 2001 |
Public
/ Agency Meeting - Canceled |
| December
5, 2001 |
Working Group Meeting:
Natural Sciences: Fisheries / Wildlife / Water Quality
Resources - (Chelan, Washington) Purpose is to discuss changes to
final management plans and to review PDEA sections and schedule |
| December
14, 2001 |
Working Group Meeting:
Cultural Resources - Canceled |
| December
19, 2001 |
Public
/ Agency Meeting - (Chelan, Washington) Purpose is to discuss
final draft comprehensive management plans, review progress on
agreement documents and discuss revisions to PDEA |
|
|
|
|
|
*Tentative |
|