Plans
Article 404 - Lake Chelan Fishery Plan
-
June 30, 2011 -
2011 Annual Work Plan
, acknowledgement of receipt from FERC
-
June 1, 2011 -
2011 Annual Work Plan
, submittal to FERC
-
July 22, 2010 -
2010 Annual Work Plan
, acknowledgement of receipt from FERC
-
May 27, 2010 -
2010 Annual Work Plan
, submittal to FERC
-
March 26, 2009 -
2009 Annual Work Plan
, acknowledgement of receipt from FERC
-
February 17, 2009 -
2009 Annual Work Plan
, submittal to FERC
-
April 28, 2008 -
2008 Annual Work Plan
, acknowledgement of receipt from FERC
-
April 17, 2008 -
2008 Annual Work Plan
, submittal to FERC
2008
-
December 4, 2007 -
Lake Chelan Fishery Plan
, order modifying and approval from FERC
-
November 6, 2007 -
Lake Chelan Fishery Plan
, submittal to FERC
Reports/Studies
Article 404 - Lake Chelan Fishery Plan
Article 405 - Operations Compliance Monitoring Plan
Article 405(a) - Flow/Lake Level/Ramping Rate Reports
-
October 21, 2011 -
Minimum Flow and Ramping Rate Deviations (May 15 and 17, 2001)
, response from FERC
-
September 29, 2011 -
Lake Level Target Deviation (May 1, 2011 and June 1, 2011)
, response from FERC
-
September 28, 2011 -
Minimum Flow and Ramping Rate Deviation (April 18, 2011)
, response from FERC
-
June 29, 2011 -
Lake Level Target Deviation Report (June 1, 2011)
, submittal to FERC
-
June 16, 2011 -
Minimum Flow and Ramping Rate Deviation Report (May 15 and 17, 2011)
, submittal to FERC
-
June 2, 2011 -
Lake Level Target Deviation Notice (June 1, 2011)
, Chelan PUD email notification
-
May 31, 2011 -
Lake Level Target Deviation Report (May 1, 2011)
, submittal to FERC
-
May 19, 2011 -
Minimum Flow and Ramping Rate Deviation Report (April 18, 2011)
, submittal to FERC
-
May 19, 2011 -
Minimum Flow and Ramping Rate Deviation Notice (May 15 and 17, 2011)
, Chelan PUD email notification
-
May 2, 2011 -
Lake Level Target Devviation Notice (May 1, 2011)
, Chelan PUD email notification
-
April 20, 2011 -
Minimum Flow and Ramping Rate Deviation Notice (April 18, 2011)
, Chelan PUD email notification
-
January 14, 2010 -
Minimum Flow Deviation (October 24 - 26, 2009)
, response from FERC
-
November 25, 2009 -
Minimum Flow Deviation Report (October 24-26, 2009)
, submittal to FERC
-
October 28, 2009 -
Minimum Flow Deviation Notice (October 24-26, 2009)
, Chelan PUD email notification
Projects
Lake Chelan Food Web Model
Monitoring and Evaluation Activities
Tributary Barriers