Learning Center
Alcoa Proposed Term Sheet Notebook
The following information was presented to PUD Commissioners June 16, 2008. All documents are in .pdf format.
3. Amendment No. 2 to the Industrial Power Sales Agreement
4. Memo to Board re: Proposed PSA and Transmission Agreements 6-16-08
The following information was presented to PUD Commissioners on Oct. 15. All documents are in .pdf format.
1. Proposed timeline of discussions
2. Brief history of Chelan PUD and Alcoa
3. Pie chart of proposed portfolio approach
4. Proposed term sheet with Alcoa
5. Alcoa’s letter regarding plant investments, facilities study, committed to expenditures to keep plant operating through 2028
6. Memo from District’s power contract negotiating team describing the major points of proposed term sheet
7. Puget power sales agreement
- December 5, 2005 memo describing major points
- January 3, 2006 memo re: template aspects of Puget PSA
- Resolution No. 06-12830 approving Puget PSA and template provisions
9. Load-Resource balance projections to 2032
10. Future surplus scenarios, post-2012 examples. Scenarios intended for future discussions with Board in 2008 about portfolio approach and potential contracts with other counterparties
11. Risks to the District that are mitigated by or recognized in the Alcoa proposed term sheet
12. Transmission constraints (map)
13. Economic evaluation of Wenatchee Works by CRU Strategies (international metals consultant) dated 4-12-07
- Conclusion of report: power supplied pursuant to the proposed term sheet to run three pot lines would increase probability that Alcoa will find it economically feasible to operate Wenatchee Works on a sustained basis over the terms in the proposed term sheet (2028) - Available upon Request
14. Economic value of Alcoa to the community:
- Real estate taxes paid by Alcoa per Chelan County Treasurer
- Jobs and economic multiplier
15. Cost compared to market - Three scenarios
- Memo to Board re: Proceeds from the Sales of Surplus Energy
- Rating Agency Views on Long-Term Take and/or Pay Contracts
- Colockum's Resources Portfolio (Exhibit E from 2004 Contract)
- Highlights: Alcoa proposed term sheet
- Information in Response to Customer Request Dated October 25, 2007
-
Performing Arts Center Letter in Support
- Additional Recognition for Alcoa
- Answer to Customer Question re: Average Smelter Power Cost - 2006
- Rating Agency - Bond Counsel's Perspective