License Documents by Article
Article 401 - Scheduling and Reporting Requirements and Amendment Applications
Article 1(a)(1) - Erosion Control Implementation Plan
Article 1(a)(2) - Site Specific Erosion Control Plans
-
March 29, 2010 -
Site Specific Erosion Control Plan (Sites 24, 25, 26, and 27)
, approval from FERC
-
November 18, 2009 -
Site Specific Erosion Control Plan (Sites 24, 25, 26, and 27)
, submittal to FERC
-
December 14, 2007 -
Erosion Control Implementation Plan
, approval from FERC
-
November 6, 2007 -
Site Specific Erosion Control Plan (Sites 11, 55, 58, and 59)
, submittal to FERC
Article 1(a)(3) - Erosion Monitoring and Maintenance
Appendix A, Article 10(f) - Traditional Cultural Properties Management Plan
-
October 11, 2011 -
Traditional Cultural Properties Management Plan
, submittal to FERC
-
May 10, 2011 -
Traditional Cultural Properties Management Plan
, third request for extension of time granted by FERC
-
November 8, 2010 -
Traditional Cultural Properties Management Plan
, request for third extension of time submittal to FERC
-
October 2, 2008 -
Traditional Cultural Properties Management Plan
, second request for extension of time granted by FERC
-
September 15, 2008 -
Traditional Cultural Properties Management Plan
, request for second extension of time submittal to FERC
-
September 14, 2007 -
Traditional Cultural Properties Management Plan
, time extension granted by FERC
-
August 1, 2007 -
Traditional Cultural Properties Management Plan
, time extension submittal to FERC
Article 403 - Stehekin Area Implementation Monitoring Plan
-
August 2, 2011 -
Stehekin Riparian Zone Plan
, approval from FERC
-
April 29, 2011 -
2011 Stehekin Work Plan
, submittal to FERC
-
November 1, 2010 -
Stehekin Riparian Zone Plan
, submittal to FERC
-
April 8, 2010 -
2010 Stehekin Work Plan
, submittal to FERC
-
November 20, 2009 -
Riparian Zone Action Plan
, order granting extension of time from FERC
-
September 15, 2009 -
2009 Work Plan
, acknowledgement of receipt from FERC
-
August 13, 2009 -
Riparian Zone Action Plan
, time extension request submittal to FERC
-
March 25, 2009 -
2009 Work Plan
, submittal to FERC
-
May 6, 2008 -
Stehekin Area Implementation Monitoring Plan
, order modifying and approval from FERC
-
November 6, 2007 -
Stehekin Area Implementation Monitoring Plan
, submittal to FERC
Article 404 - Lake Chelan Fishery Plan
-
June 30, 2011 -
2011 Annual Work Plan
, acknowledgement of receipt from FERC
-
June 1, 2011 -
2011 Annual Work Plan
, submittal to FERC
-
July 22, 2010 -
2010 Annual Work Plan
, acknowledgement of receipt from FERC
-
May 27, 2010 -
2010 Annual Work Plan
, submittal to FERC
-
March 26, 2009 -
2009 Annual Work Plan
, acknowledgement of receipt from FERC
-
February 17, 2009 -
2009 Annual Work Plan
, submittal to FERC
-
April 28, 2008 -
2008 Annual Work Plan
, acknowledgement of receipt from FERC
-
April 17, 2008 -
2008 Annual Work Plan
, submittal to FERC
2008
-
December 4, 2007 -
Lake Chelan Fishery Plan
, order modifying and approval from FERC
-
November 6, 2007 -
Lake Chelan Fishery Plan
, submittal to FERC
Article 405 - Operations Compliance Monitoring Plan
Article 406 - Wildlife Habitat Plan
-
April 29, 2011 -
2010 Activity Report and 2011 Work Plan
, submittal to FERC
-
June 8, 2010 -
2010 Wildlife Work Plan
, acknowledgement of receipt from FERC
-
April 30, 2010 -
2010 Wildlife Work Plan
, submittal to FERC
-
October 2, 2009 -
2009 Wildlife Work Plan
, acknowledgement of receipt from FERC
-
April 27, 2009 -
2009 Wildlife Work Plan
, submittal to FERC
-
April 10, 2008 -
Wildlife Habitat Plan
, modifying and approval from FERC
-
November 6, 2007 -
Wildlife Habitat Plan
, submittal to FERC
Article 407 - Recreation Resources Management Plan
Article 408 - Threatened and Endangered Species Protection Plan